Skip To Main Content

RFP

2023 Gymnasium Expansion RFP
First page of the PDF file: 20231108GymnasiumExpansionRFP01-2023_NCAv3boardapproved_1

RFP Q&A

 

QUESTION ANSWER
Confirm that NCA is not requesting financing for the project from bidders. NCA is not requesting project financing from the bidder.
We have one RFP clarification- section 7. Do you see these costs as the costs for preparing the construction documents, administering the pre-construction collaboration, and then a fee for construction costs much like a Construction Manager at Risk? Section 7 of the RFP requests the bidder to provide any and all detailed costs for the project that the school would be expected to pay.

 

 

School Tour

Potential bidders are invited to tour the school facility on January 9, 2024 at 10:00 A.M.

All visitors must check in with valid identification at the front office prior to the tour.

Proposals Received

Heatherwood Construction Company

Summit Construction Group

Owen Ames Kimball

PBS